September 5th, 2011 by Joe BurgessDrew Memorial Hospital’s phase I and Phase II of the building modernization project were discussed. The new inpatient wing under construction should be completed and ready for occupancy by February 1, 2012. The allied health building should be completed and ready for occupancy by March 1, 2012. The final phase of this project, which is the new surgery center and a new concept and a line drawing, was reviewed. A cost estimate should be available within the next few weeks, based on the new concept of locating the Women’s Center on the front side of the hospital rather than on the backside and relocating the new geri-psych unit closer to the hospital.
Reports indicate that the construction of the new Pre-Post/Op area should be complete by October 1, 2011.
Reprinted from DMH Hospital Report.